Light Rail for Cheviot is Cheviot Hills Homeowners advocating use of the existing “Exposition Right of Way” south of Northvale Road at the edge of our neighborhood


 

PHASE I

PHASE II

Metro/Expo Board chooses alternatives to study and awards Environmental Consulting Contract (for preparation of Environmental Impact Report (EIR) and Environmental Impact Statement (EIS) and Alternative Analysis (AA)

Feb 2000

Nov 2006

Public Scoping Meetings and Comment Period

 

May 23, 2000
through
June 23, 2000

February 27, 2007
through
April 2, 2007

Public Review of Draft EIR and EIS

 

April 6, 2001
through
June 15, 2001

Winter 2007/2008

Approval of Draft EIR and EIS; Locally Preferred Alternative adopted; Drafting of Final EIR begins that requires refined station-area planning and development of required mitigation measures

June 2001

Spring 2008

Preliminary Engineering begins

2003

Spring 2008

Public Circulation of Final EIR and EIS

Through
November 28, 2005

April 2009

Certification of Final EIR and EIS

December 2005

Spring 2009

Record of Decision (approval) from Federal Transportation Administration

February 27, 2006

Summer 2009

Construction starts (groundbreaking)

September 29, 2006

Fall 2009

Operations start

June 2010

Summer 2013

 

All times in the future are, of course, estimates.